This project showcases the breadth of capability within Integrated Utility Services (IUS), supporting our customer, Taylormade Timber from the initial contestable connection through to private 11kV infrastructure works and long-term asset management via an Operation & Maintenance agreement.
Our team delivered:
🔹 Over 5km of cable installation, crossing the A1 and a railway line and passing through two villages, working closely with Highways, Network Rail and local Parish Councils.
🔹 The new intake substation, fitted out and commissioned alongside Northern Powergrid and the Independent Distribution Network Operator (IDNO).
🔹 The private switch room, including earth surveys and the supply of five transformers, four of which were bespoke to the project.
🔹 The private wire 11kV network, connecting the infrastructure through to the customer.
🔹 The customer was then onboarded onto an ongoing IUS Operation & Maintenance agreement, providing continued support for inspection, maintenance and emergency call-out and fault repair.
From the High Voltage contestable connection and substation construction, through to the private 11kV network delivery, commissioning and ongoing maintenance, IUS provided a complete end-to-end solution.