As Storm Darragh swept across the region at the weekend with winds of up to 75mph, the IUS Overhead Line (OHL) Team was on the frontlines, stepping up to support Northern Powergrid in their response. 🌲⚡

Deployment Highlights:

Saturday (7 Dec): We rallied to areas around Durham and Darlington, tackling damage caused by storm conditions and fallen trees. Thousands of Northern Powergrid customers had their supplies restored through our teams who worked hard into the early hours.

Sunday (8 Dec): Teams were redeployed to the harder-hit North Yorkshire region, addressing multiple LV and HV pole faults and worked into the night.

Monday-Wednesday: From Kirkbymoorside to Scarborough, our teams safely worked around the clock to help restore supplies for customers.

A big Thank You to our dedicated OHL team...

💬Ben Stokoe, Head of Operations: “Thank you and well done to everyone in the OHL team, both direct and subcontract. Your hard work and dedication in these extremely difficult circumstances are truly appreciated.”

💬Reece Johnstone, OHL Operations Manager: “The overhead linesmen, plant operatives, and back-office staff have demonstrated exceptional dedication. Your efforts are what make restoring supplies to affected customers possible. Well done to everyone involved!”

News Image
IUS Storm Darragh
summary
As Storm Darragh swept across the region at the weekend with winds of up to 75mph, the IUS Overhead Line (OHL) Team was on the frontlines, stepping up to support Northern Powergrid in their response. 

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

IUS proud to support Yorkshire Water on a milestone project
IUS proud to support Yorkshire Water on a milestone project
Integrated Utility Services (IUS) has successfully completed the High Voltage (HV) replacement works at Yorkshire Water's Langsett Raw Water Pumping Station (RPS) and Marsh Water Pumping Station (WPS) sites, installing Schneider Electric’s new SF₆‑free AirSeT 11kV switchgear in place of the ageing Igranic units.
Substation Installation at Northern Gas Networks’ NeRV site
Substation Installation at Northern Gas Networks’ NeRV site
Last week, our team at Integrated Utility Services were on site at Northern Gas Networks’ NeRV (Net Zero Research Village), working on the final 11kV cable jointing and terminations, testing and commissioning ahead of the site being energised.
IUS Industrial Stand Down Q1
IUS Industrial Stand Down Focuses on Commitment to Safety in 2026
On Friday, we brought our Industrial teams together at Ripon Racecourse for our Integrated Utility Services Industrial Stand Down, taking time to step back, reflect and align on our priorities for the quarter ahead.