Unilever, Leeds Supply Upgrade 11kV Contestable Connection & Private Infrastructure Works

case-study

IUS completed the electrical construction works associated with Unilever’s supply upgrade at ...

Client

Unilever

Project

Unilever, Leeds Supply Upgrade

Location

Unilever, Coal Lane, Leeds

SERVICES PROVIDED
  • Outline and detailed design
  • 11kV Contestable connection work
  • On site private 11kV infrastructure work
  • Procurement of equipment
  • Installation of DNO and private 11kV switchgear
  • Installation of 11kV cables
  • Modifications of the existing 11kV ring
  • Heavy lifting operations
  • Testing and commissioning
  • Preparation of handback documentation
OVERVIEW

IUS completed the electrical construction works associated with Unilever’s supply upgrade at their site in Leeds. In order to provide a 4.3MVA supply, a new 11kV Distribution Network Operator (DNO) substation was required, as well as new private 11kV switchgear and transformers. IUS were appointed to undertake the design and installation of the 11kV contestable elements of the connection works along with the private 11kV and LV infrastructure.

DESCRIPTION

The project involved extending the DNO’s local 11kV network c. 220m to a point on Unilever’s site and supplying and installing a new 11kV intake substation complete with an 11kV metered ring main unit.

Modifications to the existing 11kV private network were required to facilitate the connection upgrade as well as the supply and installation of an 11kV switchboard, local 11kV ring main units, 11,000/433V transformers and a low voltage switchboard. Due to the nature of the site, IUS were required to work to a tight programme. The contract was delivered to the agreed timescales.

DOWNLOAD PDF VERSION

Careers in IUS

Read More

/sites/default/files/2023-09/careers_2_0.jpg

IUS News

Major Incident Response: Storm Bert
Yorkshire Water Developer Day at University of Bradford Stadium
IUS are Carbon Neutral